Distance Between Buildings, Courtyards and Compound Walls
A-007 · R01 · Awaiting human acceptance
Two buildings on one plot can meet their boundary setbacks and still be too close together. Their separation depends on whether the facing sides supply light and ventilation. A courtyard has its own minimum dimensions. Walls and gates along the plot edge are controlled separately.
Space between buildings #
Without light or ventilation taken from the facing sides, the minimum separation is 3 m. Where light and ventilation are taken from those sides, the minimum is half the mean height of the buildings or 3 m, whichever is greater, measured where the light and ventilation are taken. Only chajjas or weatherboards may project into that minimum distance under 4.8(b). For buildings 10 m and 14 m high, the mean is 12 m and the required distance under (b) is 6 m. [Regulation 4.8.]
Light and ventilation through a courtyard #
A courtyard is an open-to-sky space used for light and ventilation and enclosed or partly enclosed by a building or boundary walls. It may start at any floor within or beside the building and must be accessible from that floor. [2(42).]
For habitable rooms drawing light and ventilation from it, the court must cover at least 10 m². Its smallest side must also satisfy the height-dependent side setback in Table IV. For non-habitable rooms, a court up to 11 m high needs at least 6.25 m² and a smallest side of 2.5 m. Above 11 m it needs at least 9 m² and a smallest side of 3 m. Additional building height can change the applicable distance or court dimension even if the footprint stays the same. See Setbacks, Building Lines and Projections. [4.9(a)–(b), 4.4.2.]
Walls, fences and gates #
A boundary wall follows the property perimeter. A compound wall encloses the property, includes its gates and may be made of any material. The definition of fencing refers to the compound wall. Permission may be sought separately or with the building application. The detailed drawings are at 1:100. [2(19), (40), (57), 11.1.]
The usual maximum is 1.80 m on a non-street boundary and 1.50 m on a street boundary, with closed construction up to 0.90 m only on the street side. A wall in front of an existing or proposed commercial establishment requires separate entry and exit points. At a street junction the wall must preserve statutory sight distance. For 9 m along both sides from the plot corner it must stay within 1 m above the crown of the road. [11.2–11.3 and 4.3.]
Government or semi-government blocks requiring special security, mills, factories, industrial units, storage depots and warehouses may be allowed walls up to 3 m above the road crown if traffic sightlines remain clear. Industrial estates and industrial areas have a specific 3 m maximum, with solid construction up to 2 m and the remaining 1 m in barbed wire or chain link subject to the sightline. The general provision prohibits barbed-wire fencing and cactus hedges on public-road boundaries. Editor’s note. For a public-facing industrial boundary the text contains both provisions. The provisions do not expressly settle whether the industrial allowance overrides the public-road prohibition. [11.4, 11.7, 11.10.]
Gates open inward unless recessed far enough to avoid projecting beyond the wall line. At the intersection of roads 10 m wide or more, entry or exit must be at least 15 m from the tangent point, or at the farthest end if the plot side is too short. Street-facing sheet-metal fences need design approval by the Licensing Authority. The wall must respect the right of way in the designated plan and preserve traditional access across the plot. [11.5–11.9.]
Access and Circulation Within a Plot explains the junction sightline. See the official GLDBCR, Regulations 2(19), (40), (42), (57), 4.8–4.9 and 11. Check the current official regulations and notified plan before making a regulatory decision.