The application package depends on the work proposed and on the authority handling it. A new building, a change of use and a subdivision use different drawings. The forms also distinguish what the applicant submits from the orders issued by the authority.
The application package #
An application is made in the form prescribed by the authority. Under Regulation 2(10), ‘approved’ refers to sanction by the authority under the regulations. The defined planning instrument in 2(97) is a Regional, Outline Development, Comprehensive Development or Zoning Plan or other government-approved plan or scheme. Drawings submitted with the application have a different function: they describe the proposed development against that legal basis. [GLDBCR 2(5), (10), (97).]
Regulations 3.2A–B require the relevant A1-PDA, A1-TCP, A2 or A3 application and the B1 questionnaire. The planning and licensing paths are explained in Development Permissions and Clearances. Appendices A1 and the applicable forms also identify copy counts, power of attorney and external NOCs where relevant.
Regulation 3.2D requires evidence of title or sufficient interest, where applicable: original survey plan or approved-subdivision plan or approval reference including Technical Clearance, record of rights in Form III or I & XIV or city-survey register, and the relevant sale, gift, lease, mortgage or other instrument. The authority may waive particular documents if satisfied with the others. The owner's B4 affidavit confirms title documents. A competent professional signs the B2 conformity certificate. Under 3.2D(d), a structural engineer provides the B3 structural liability certificate. The printed Chapter 26 index describes B3 under engineer or structural engineer. The operative signing and competence provisions govern. Include an existing conversion sanad or A4 application with the conversion-area and location plans in four copies each, and a construction-cost certificate at notified rates for licence fees. [3.2D(a)–(f).]
Drawings for building operations #
For an area up to 4,000 m², the site plan is at 1:500 or larger. Above 4,000 m² it is at 1:1,000 or larger. It shows boundaries, dimensions, north, existing and proposed structures on, over, under or projecting beyond the plot, access from street and access to the rear with widths, road widening, setbacks, open space, distances between buildings, B1 area statement and natural features including drains, water bodies and trees. It locates septic tank, soak pit, lines and inspection chambers, distance to the nearest well, existing and proposed wells, and any water sump. [3.2C1(a).]
Detailed plans at 1:100 or 1:50 show every floor, room and framing dimensions and spacing, stairs, ramps, lift wells and uses. Submit elevations from all streets, at least the front, a section through the stair, a roof drainage plan and septic/soak pit dimensions and construction details under the Health Act. For repetitive units, submit one unit at 1:100 or 1:50 and block plan, elevation and section of all units at 1:200 with overall dimensions. Plans may be permitted at 1:200 for a floor plate over 500 m². A location plan has written distances and prominent landmarks and need not be to scale. [3.2C1(b)–(c).]
Except for a single-family dwelling, the parking drawing shows dimensions, exact positions, number and circulation direction at 1:500, or 1:250 on plots below 2,000 m². Cuts or fills over 1.50 m from existing ground need plans and sections. Sloping sites require 1 m interval contours prepared by a Chartered Surveyor, Engineer or Architect. Site Constraints and Sloping Land explains the separate gradient, area and benchmark rules. In a conservation zone include the relevant external elevation with an adjacent elevation or its latest photo, coloured postcard-size photos of existing buildings and both neighbours, and the exterior and compound-wall colour scheme. [3.2C1(d)–(g).]
Drawings for other application types #
Engineering, mining and quarrying use a 1:1,000 or larger site plan with boundaries, north, existing structures on, over, under or beyond the site, natural features, street access and width and exact operations. Include a dimensioned landmark location plan, cuts or fills over 1.50 m in plan and section, 1 m contours from a Chartered Surveyor on sloping sites, and Forest Department tree-felling permission if applicable. Regulation 7 adds a separate site-plan and geotechnical requirement for the operations it covers. [3.2C2.]
For a material change of use, use the 4,000 m² scale break for the site plan and show boundaries, dimensions, north, structures and street and rear access with widths. Provide the affected building portion with existing uses and the precise change. [3.2C3.]
Township or subdivision approval begins with the provisional layout and moves to final approval after conditions are complied with. Provisional drawings are at 1:500 or larger, or 1:1,000 or larger above 50,000 m². They show boundaries, dimensions, north, street access, numbered plots and footprints, plot and open-space dimensions and area, internal road widths and areas served, B1 statement, existing structures and natural features, road sections with drive, footpath, shoulders, drains and materials, cross-drain size, location and sections, and service-duct layouts and construction. Include the dimensioned landmark location plan, sections for cuts or fills over 1.50 m and surveyor’s 1 m contours on sloping sites. Final drawings at 1:500 or larger show the same site and layout particulars as executed and include the NOCs stipulated at provisional approval. [3.2C4.]
Dimensions, sheet sizes and colour #
Site-plan dimensions are written in metres and detailed-plan dimensions in centimetres. The drawing rule specifies five sets or as required by the authority, generally two to PDA or TCP, one to the local body and two to the owner. Check the application’s specific copy schedule. Accepted sheets are A0 (841 × 1,189 mm), A1 (594 × 841), A2 (420 × 594), A3 (297 × 420), A4 (210 × 297) and A5 (148 × 210). [3.2C4 Note and 3.3.]
Item | Notation |
|---|---|
Plot boundary | Black |
Proposed work and alteration | Red |
Open space and access to building and rear | Green |
Work to be demolished or removed | Brown |
Water supply and drainage or sewerage | Yellow |
Deviation | Red broken line |
Cutting and filling | Red/yellow as printed |
Trees | Dark green |
Source. GLDBCR 3.4, Table I. The colours apply to plans, amended plans and completion plans.
Who signs and authenticates #
The owner signs the application, questionnaire, building or development plans and structural design and drawings, with name in capitals, addresses and telephone if any. Professional signatories include name, address and registration number and act within their competence. Architects sign the questionnaire and competent plans. Town planners, landscape architects and urban designers sign the questionnaire and township or subdivision plans within competence. Engineers and structural engineers sign the questionnaire, building and subdivision plans and structural work within competence, with structural engineers also signing structural liability and stability certificates. Engineer-diploma and civil supervisors sign the questionnaire, building and structural drawings within their competence. Owners’ and Professionals’ Responsibilities explains the underlying qualifications and registration. [3.5A.]
Copies under 3.2D are authenticated by a notary or State or Central Gazetted officer. Government can designate compulsory online or offline submission and issue by a Gazette order for development permission, technical clearance, construction licence, completion order and occupancy certificate. [3.5B–C.]
Chapter 26 form index #
Stage or record | Appendices |
|---|---|
Initial applications | A1-PDA development permission under TCP Act s.44, A1-TCP technical clearance, A2 municipal licence, A3 village-panchayat licence, A4 conversion recommendation |
Completion and registration applications | A5 completion order, A6 occupancy certificate, A7 registration or renewal, A8 registration certificate |
Questionnaire and declarations | B1 questionnaire, B2 conformity certificate, B3 structural liability certificate, B4 owner affidavit, B5 structural stability certificate, B6 professional completion certificate |
Authority grants | C1 PDA development permission, C2 TCP technical clearance, C3 municipal licence, C4 panchayat licence, C5 PDA completion order, C6 TCP completion order, C7 municipal occupancy certificate, C8 panchayat occupancy certificate |
Refusals and construction notice | C9 PDA development permission refusal, C10 TCP technical clearance refusal, C11 local building licence refusal, D1 stages-of-construction intimation |
Notary route | E1 technical clearance application, E2 completion order application, E3 registration or renewal application, E4 registration certificate, E5 conformity certificate, E6 technical clearance order, E7 completion order, E8 technical clearance refusal |
Source. GLDBCR Chapter 26, pp. 139–140. Approvals, Construction and Occupancy covers use of the forms after submission.
Additional FAR or height applications #
Annexure XIII-A Note 9 adds a comprehensive report on the project, its use and location, sustainability and infrastructure including water and power. Note 10 adds the notarised undertaking against using the grant for a four- or five-star hotel project where both road width is at least 8 m and plot area is at least 500 m². Regulation 6.1.2(b) places the applicable fee before Technical Clearance. The current fee order and rate require independent confirmation. See the 24 November 2026 Gazette and Development Permissions and Clearances.
Check the current official regulations and applicable standards before making a regulatory decision.