A plot can have a development zone under the Goa plan and also fall within a coastal regulation area. Its zone entry alone cannot establish the permitted use, FAR, height or clearance route. Coastal status depends on the applicable central notification and the approved coastal map for that location.

Which instrument governs #

Regulation 6B.3 applies the coastal regulations made under the Environment (Protection) Act, 1986, as amended. Annexure I at 27.I brings the Ministry of Environment, Forest and Climate Change’s environmental and CRZ notifications into permissions under the Goa regulations as they change. In Table VIII the CRZ entry directs the reader to Note 9, which requires strict application of the CRZ regulations in force.

The Ministry’s 6 September 2022 approval covers Goa’s coastal zone management plans at 1:25,000 scale under the 2011 CRZ Notification. The Goa Coastal Zone Management Authority is the source for approved Goa coastal maps and local clearance information. For a property, the relevant approved sheet and demarcation matter. A general description such as waterfront or a distance from the sea does not by itself identify the mapped category or resolve restrictions along tidal water bodies.

Editor’s note. The 2022 approval establishes the basis of that particular map set. The later operative notification, amendments and any replacement approved plan must be verified for the date and location of the proposal. A draft map alone cannot establish a development right.

Clearance and the state building envelope #

Regulation 3.6.2(a) requires prior approval of the Coastal Zone Management Authority where development falls in the CRZ and Environment Protection Zone described in that provision. The ordinary development permission or technical clearance and local construction licence remain separate decisions. Environmental clearance, where a central notification requires it for the project, also has its own scope. Annexure I refers to the Ministry’s notifications, including environmental clearance for the project categories and thresholds that those instruments specify.

Annexure XIII-A Note 4 expressly leaves FAR and height in CRZ areas to CRZ regulations. A qualifying approach road or an apparently eligible underlying zone cannot establish additional FAR or height that conflicts with those regulations. The GLDBCR also requires Goa Coastal Zone Management Authority approval before regularisation of unauthorised construction in CRZ can be considered. [24 November 2026 Gazette, Annexure XIII-A Note 4; note to 22.4.(a), regularisation.]

See the official GLDBCR, Regulations 3.6.2(a), 6B.3, Table VIII Note 9 and Annexure I. Check the current notifications and approved map before making a regulatory decision.