Owners’ and Professionals’ Responsibilities

Editorial review

A-029 · R01 · Awaiting human acceptance

Send feedback on this article
On this page
  1. Who can be treated as the owner
  2. Supervision and change of professional
  3. Registration and signing
  4. Architect, engineer and structural engineer
  5. Engineer-diploma and supervisor (civil)
  6. Planning, landscape and public authority roles
  7. Additional FAR or height

The owner is responsible for carrying out the work to the approved plans and ensuring supervision. The professionals who sign, design or supervise have separate responsibilities and must act within their statutory competence. The transfer of supervision matters if a professional leaves during the work.

Who can be treated as the owner #

For land or premises, a person, institution or society with sufficient interest or title under a deed or a Government or court order can be the owner. The definition also covers a person entitled to rent. It includes agents or trustees receiving rent for the owner, agents or trustees responsible for religious or charitable premises, court-appointed receivers, administrators and managers with the owner’s functions, and the specified mortgage-in-possession case. For animals, vehicles or boats it includes the person in charge at the time. Evidence of right or interest for a development application is separately required under Regulation 3.2D. [GLDBCR 2(95).]

Supervision and change of professional #

The owner or permit holder is responsible for execution in accordance with approved plans and for supervision by the professional who signed them, within the specified professional categories. A departing professional informs the competent authority in writing. The authority immediately requires the owner to appoint a replacement. The replacement takes responsibility from the date the owner and the new appointee give joint written intimation. If the owner does not appoint a replacement, the permission is suspended until appointment and intervening work is deemed invalidly undertaken. [3.12(a)–(c).]

Registration and signing #

Regulation 20 requires the listed engineering, planning and design or supervisory professionals to be registered with the Town and Country Planning Department to sign within competence. Previously authorised engineers and town planners also register afresh. Qualified professionals employed by Government departments and undertakings are excepted for specified land development and construction by Government, Government-owned corporations, autonomous bodies and local bodies. Architects provide their Council of Architecture number and declare valid registration on B2. Applications, Drawings and Forms explains which documents they sign. [20.1–20.4 and Note.]

Registration goes to the Chief Town Planner on A7. After scrutiny and the specified fee, TCP allots the registration number and issues A8. A registration is valid for five years and can be renewed with A7 and the prescribed fee. Government fixes processing fees. Negligence, failure to discharge duties or breach of the regulations may lead to temporary or permanent revocation after a show-cause notice and a reasonable opportunity to be heard. The designated Chief Town Planner registers empanelled notary architects and engineers under 20.9 for the Annexure X route. See Special Approvals, Regularisation and Government Works. [20.4–20.9.]

Architect, engineer and structural engineer #

An architect is registered under the Architects Act, 1972. Competence covers architectural building plans and information, supervision and completion certification of architectural aspects, and subdivision or layout work up to 50,000 m². Above 50,000 m² the regulation calls for endorsement by an urban designer or town planner. [2(14).]

An engineer qualifies by the specified Civil or Architectural Engineering degree or institutional or statutory membership route. The two-year experience condition applies to fresh graduate engineers within five years of graduation, under a registered engineer or structural engineer, with evidence acceptable to the registering authority. The engineer can prepare building and land-development plans and information, structural details and calculations excluding high-rises, certify supervision and completion within competence, and prepare subdivisions, layouts and services up to 50,000 m². Foreign qualifications require Indian recognition. [2(52).]

Structural engineers qualify through the stated Civil Engineering or corporate membership route with five years of design experience, an M.E. in Structures or Earthquake Engineering or equivalent with three years, or a structural engineering Ph.D. with one year. Experience is after engineer registration in a responsible structural design position. Evidence routes include client appointments and sign-offs with project details for self-employment, service or experience certificates from former Government, PSU or autonomous employment, existing structural registration, or at least five years of recognised-institute teaching in structural engineering, as specified. Evidence is subject to authority satisfaction. Competence includes structural plans, calculations and details and supervision and completion certificates for all kinds of buildings, and the stated building plans associated with land development up to 50,000 m². Regulation 3.6.2(e) separately reserves structural design or retrofitting to a Structural Engineer on Record or Structural Design Agency on Record. [2(129), 3.6.2(e).]

Engineer-diploma and supervisor (civil) #

An engineer-diploma requires a Civil Engineering diploma, five years registered as supervisor (civil), and at least ten completed projects, supported by certified planning clearance and completion records. The note permits the authority to consider specified earlier public-body registrations or Government engineer service certificates as experience without those clearance and completion records. The scope covers each building block up to 600 m² total built-up across floors and up to three storeys including stilt, if any, or height up to 9 m. [2(52A).]

A supervisor (civil) requires a Civil Engineering diploma and at least five years in building design, construction or supervision. The scope covers each block up to 300 m² total built-up across floors and up to two storeys including stilt, if any, or height up to 7.60 m. Within their respective limits both categories prepare plans and project information, structural details and calculations, certify supervision and completion, and design and supervise compound work. The definition uses ‘or’ between storey and height terms. Its wording is reproduced in sense here without deciding how a proposal that meets only one of those measures should be treated. [2(52A)–(52B).]

Planning, landscape and public authority roles #

A landscape architect has the landscape qualification described in 2(82), from a recognised Indian institution or an Indian-recognised foreign qualification. The registered role covers landscape design for land development and buildings. A town planner holds the specified recognised planning degree or diploma and is an associate member of the Institute of Town Planners, India. The scope covers township, land development and subdivision plans, calculations, details and supervision. An urban designer has a recognised postgraduate diploma or master’s in urban design or equivalent. The scope includes township and architectural plans, land development, subdivision, building details and supervision. Foreign qualifications are subject to the recognition conditions in the respective definitions. [2(82), (140), (143).]

A Government-appointed technical officer renders technical clearance for designated corporations, municipal councils or village panchayats. A Town Planning Officer is an officer of the TCP Department designated by Government for the relevant Act, Rules or Regulations. These public authority functions sit alongside the professional signing duties in Regulation 3.5A. [2(134), (141).]

Additional FAR or height #

The applicant checks proposed-height setbacks, structural safety including the capacity of an existing building, parking for added FAR, and Fire Services conformity before applying under 6.1.2(c). The Fire Services NOC is required before the construction licence application. The project proponent submits the Note 9 comprehensive report, including proposed use, local sustainability and water and power infrastructure. The notarised undertaking under Note 10 applies at road width at least 8 m and plot area at least 500 m² and excludes use of the added benefit for a four- or five-star hotel. See the 24 November 2026 Gazette and Floor Area Ratio. [Annexure XIII-A Notes 9–10.]

Check the current official regulations and applicable standards before making a regulatory decision.