Building Height and Roofs
A-010 · R08 · Awaiting human acceptance
On this page
- How Building Height Is Measured
- Maximum Height by Plan and Zone
- Regional Plan Settlement Areas
- Zone Height Limits
- Additional Height by Government Approval
- Additional height schedule
- Eligibility and Conditions
- Legislative History of Additional Height
- How Building Height Affects Setbacks
- Buildings on Stilts, Basements and Sloping Ground
- Where the Ground Slopes
- Rooftop Features and Fire-Safety Height
- Special Places and Building Types
- How Much of a Roof May Be Flat?
A building’s permissible height depends on the applicable plan and zone. Its measured height depends on where the measurement starts and whether the roof is flat or sloping. A building on stilts or above a basement may also need a separate height measurement for fire safety. In residential zones, the regulations limit how much of each building’s roof may be flat.
How Building Height Is Measured #
Building height is the vertical distance from plinth level to the top of the building. The plinth is the part of the building between the surrounding ground and the floor immediately above it. Height of the building is another name for the same defined measurement. Regulations 2(23), 2(76) and 2(99)
The general calculation starts at the top of the plinth, which the height provision describes as no more than 0.90 m above the adjoining road. A flat roof is measured to the top finished level of the uppermost roof slab. A sloping roof is measured to the eaves, where the outside face of the outer wall meets the finished roof surface. In the basic flat-land case, the flat-roof measurement runs from the top of the plinth to the top of the uppermost slab. Regulation 6A.5, opening and clauses (a)–(b)
For example, the top of the plinth is ±0.00 m on the drawing and the finished roof slab is at +11.50 m. The building height is 11.50 m. For a sloping roof, the building height is also 11.50 m if the outside face of the outer wall meets the finished roof at +11.50 m, even if the ridge is higher. Some conservation limits separately specify overall height. Regulation 6A.5(a)–(b) and Table IX
A residential building’s plinth must be at least 0.45 m above the top of the access or pathway near its entrance. For other buildings the Competent Authority may relax this requirement, and the ground floor may be permitted on pillars or stilts instead of a solid plinth. The provision also allows a 0.45 m minimum plinth for rooms such as a sanitary block, pump room or air-conditioning plant room. A garage used only for parking may have no plinth. Regulation 13.9
Maximum Height by Plan and Zone #
The maximum depends on the applicable plan and the plot’s zone. In Regional Plan settlement areas, the village panchayat category matters. In areas covered by an Outline Development Plan or zoning plan, the zone is the starting point. Table VI identifies the zone designations used for the listed plan types and schemes. Each part of a plot that falls in a different zone is subject to its own zone’s height rule. Regulations 6.1.1 and 6A.4, Table VIII Note (19)
Regional Plan Settlement Areas #
Table V now applies to any plot area. VP1 height follows S2/R2, which is 11.50 m; VP2 height is 9.00 m including the stilt. The 24 November 2026 amendment replaces 'Area below 4000m²' with 'Any Area' wherever occurring in Table V. A plot of exactly 4,000 m² or above therefore falls within the amended plot-area wording. The table’s remaining note covers residential, commercial, industrial and institutional buildings. Additional height requires the separate approval framework explained below. Source: Table V, Table VIII S2/R2, and 24 November Gazette §2(i), p.2201.
Table V Note (2) is omitted from 24 November 2026. The current additional FAR and height framework is Regulation 6.1.2 and Annexure XIII-A. Gazette §2(ii)–(iii), pp.2201–2202.
Zone Height Limits #
Zone | Maximum height or qualification |
|---|---|
Residential S4/R4 · S3/R3 · S2/R2 · S1/R1 | 7.60 m · 9.00 m · 11.50 m · 15.00 m, respectively |
Special Residential (SPR) | 28.00 m |
Commercial C4 · C3 · C2 · C1* | 9.00 m · 15.00 m · 20.50 m · 24.00 m, respectively |
CS · C1 Special · SPC | 32.00 m · 32.00 m · 40.00 m, respectively |
Recreational R (RG in ODP or zoning plans) | 5.00 m or as technically required for the use |
Agricultural A1 and A2 | 7.60 m. Separate farmhouse provisions apply. |
Traffic and Transportation (T) | 15.00 m |
Public (P) | 15.00 m in the table. See the 16.00 m note below. |
Industrial I1, I2 and I3 | 15.00 m. A relaxation may apply for qualifying industrial needs. |
Coastal Regulation Zone (CRZ) | Applicable CRZ regulations govern. |
Source Regulation 6A.4, Table VIII, printed pp. 62–64, and Notes (1), (3), (9), (14), (15) and (27) · 9 August 2023 Gazette, third notification §4 · 29 November 2024 Gazette §2.
Table VIII marks C-1 with an asterisk. Note (1) identifies the central business districts demarcated in the Outline Development Plans of Panaji, Margao, Mormugao, Mapusa and Ponda. The C-1 entry therefore needs its designated-plan context. Table VIII Note (1).
Zone P has a 15.00 m entry in the table, while both Table VIII Note (15) and Table VII Note (4) state a 16.00 m maximum. The two notes expressly support 16.00 m, so the table’s 15.00 m should not be presented as an uncontested absolute ceiling. No correcting instrument was located in this bounded check. Where a proposal depends on the difference, the applicable figure remains subject to competent-authority confirmation; this article does not silently replace either printed value. The industrial rows share a 15.00 m height cell in the printed table. In industrial zones, height can be relaxed for processing requirements. A specific industrial relaxation also covers operational needs and plant or machinery and requires written reasons from the Competent Authority. The November 2024 amendment to the industrial note adds approval-based relaxations for FAR, setbacks, parking and coverage on Goa Industrial Development Corporation plots. The amendment makes no change to the height wording. Table VII Note (4), Table VIII Notes (3) and (15), and Regulation 22.4(a) · 29 November 2024 Gazette §2
In IT parks established by the Government of India’s or Goa’s information technology department, IT/ITES on plots or premises abutting a road more than 10.00 m wide has a height limit of 24.00 m and a maximum FAR of 200 under the special note. A road exactly 10.00 m wide does not meet that note’s condition. Permissions and clearances in SPR, CS and SPC are subject to Government approval and fulfilment of fire-safety requirements by the Directorate of Fire and Emergency Services. Table VIII Notes (14) and (27)
Additional Height by Government Approval #
Additional height may be considered for development on plots of at least 300 m² in municipal, planning and village areas, on the TCP Board’s recommendation and Government approval. The Government may reject an application with recorded reasons. The allowance depends on the base permissible FAR and road width, with the additional height measured above the permissible height under Regulation 6A.4, Table VIII. Regulation 6.1.2(a), (d), (f) and Annexure XIII-A, inserted 24 November 2026.
Additional height schedule #
Base FAR¹ | Road width (m) | Additional height up to (m) |
|---|---|---|
Up to 60 | 6 ≤ width < 8 | 5.90 * |
Up to 60 | 8 ≤ width < 10 | 5.90 * |
Up to 60 | width ≥ 10 | 9.00 |
80 | 6 ≤ width < 8 | 3.40 * |
80 | 8 ≤ width < 10 | 3.40 * |
80 | width ≥ 10 | 11.50 |
100 | 6 ≤ width < 8 | — |
100 | 8 ≤ width < 10 | — |
100 | width ≥ 10 | 15.00 |
150 | 6 ≤ width < 8 | — |
150 | 8 ≤ width < 10 | — |
150 | width ≥ 10 | 19.50 |
200 | width ≥ 10 | 16.00 # |
250 | width ≥ 10 | 8.00 |
The base FAR column follows the Annexure’s reference to Table VIII. Exactly 8 m enters the 8–below-10 m band, and exactly 10 m enters the 10 m-and-above band. Dashes are retained from the Gazette and give no positive allowance for extra height.
* The starred rows have a total height cap of 14.9 m. # For SPR, the additional height is limited to 12 m and total height to 40 m. The general total height cap is 40 m, subject to the lower limits and extra-height allowance in the applicable row. The total FAR cap is 300. The full combined FAR and height schedule is in the FAR article. Annexure XIII-A, table, footnotes, Notes 11–12.
For example, for base FAR 100 on a road at least 10 m wide, up to 15 m additional height may be considered. If the applicable baseline height is 15 m, that gives up to 30 m before other controls, rather than an automatic 40 m. For SPR, the baseline 28 m plus the specific additional-height cap of 12 m gives the overall ceiling of 40 m. Each example depends on eligibility, approval and the applicable height measurement.
Eligibility and Conditions #
Eligible zones are Residential/Settlement, Commercial, Industrial excluding GIDC industrial estates and industrial areas, Public/Semi-Public/Institutional, Transport, Warehousing and Communication. The route excludes four- and five-star hotels and protected-monument buffer zones; CRZ controls continue to govern CRZ land. Projects on roads at least 8 m wide and plots at least 500 m² require a notarised undertaking that the additional FAR and/or height will not establish a four- or five-star hotel. Annexure XIII-A, Notes 1–4 and 10.
Height-related setbacks must be available. Structural safety must be satisfied, including capacity of existing buildings to support additions. Parking is required for the additional FAR and Fire and Emergency Services requirements apply, with its NOC before application for construction licence. Regulation 6.1.2(c). These conditions accompany the height allowance even where the underlying technical requirements are explained in other articles.
Rainwater harvesting is mandatory. Rooftop solar PV and/or solar water heating must cover at least 5% of total sanctioned load, including existing load, irrespective of plot area. Editor’s note. Note 7 prints 14.1.3(c), which concerns well parapets in the consolidation. The baseline solar provision is 14.3.1(c). The scheme condition remains explicit. Water, Drainage, Power and Rainwater Harvesting explains the service requirements. An STP is mandatory above 9.7 KLD total occupant water consumption, including the additional FAR occupants, in areas without sewer lines; Government may relax this for previously granted proposals. A comprehensive project report must address development, use, locational sustainability and all necessary infrastructure, including water and power sourcing. Technical Clearance or Development Permission must follow the regulations in force. Annexure XIII-A, Notes 5–9.
Fees specified by Government order are payable before Technical Clearance. Prior additional FAR/height grants in PDA and non-PDA areas must be examined and regularised under 6.1.2(e). Cooperative redevelopment under section 104A of the Goa Co-operative Societies Act, 2001 is included, with possible further case-specific Government relaxations. Regulation 22.4(c) also permits additional FAR for the industrial and specified Government/public-scheme projects described in 22.4(a)–(b), on the fee basis in 6.1.2. This separate wording requires care alongside the Annexure’s GIDC/industrial-area exclusion.
Editor’s note — unresolved implementation points: the current fee order under 6.1.2(b), current court effect, and interaction of 22.4(c) with the Annexure exclusions have not been independently confirmed. The enabling clause includes village areas while the Annexure table names Table VIII base FAR; authority confirmation is needed where application to a Table V proposal is unclear.
Source: Regulation 6.1.2(a)–(f) and Explanation, 22.4(c), Annexure XIII-A table, footnotes and Notes 1–13, Gazette pp.2201–2204. https://drive.google.com/file/d/1OlWrflOzsKXJCP_kB3555TgYxLqNq8c6/view
Legislative History of Additional Height #
The 24 November 2026 amendment comes into force at once. It replaces the Table V plot-area wording with “Any Area” and omits Note 2, resolving the former surviving-row boundary issue for Table V. The 2023 insertion and corrigendum, and the ₹1,000 per m² rate recorded in the July 2025 order, remain historical sources for the previous scheme. That earlier rate is not asserted as the applicable charge under new 6.1.2(b).
How Building Height Affects Setbacks #
The minimum side and rear setbacks generally increase with building height. For example, Table IV pairs an 11.50 m building with a 4.00 m setback and a 15.00 m building with a 5.00 m setback. The table below gives the values listed in the regulation.
Building height | Minimum side and rear setback |
|---|---|
7.60 m | 3.00 m |
9.00 m | 3.50 m |
11.50 m | 4.00 m |
15.00 m | 5.00 m |
18.00 m | 5.50 m |
21.00 m | 6.00 m |
24.00 m | 6.50 m |
28.00 m | 7.40 m |
32.00 m | 8.00 m |
36.00 m | 8.00 m |
Above 36.00 m, the note adds 1.00 m to the side and rear setbacks for every additional 4.00 m of building height. The note describes the maximum that authorities may insist on as “atleast 15.00 mts.” The wording leaves the effect of that proviso unclear. The table and note also leave the treatment of heights between listed values or between 4.00 m increments unstated. (Regulation 4.4.2, Table IV and note.)
Separate side-setback provisions apply in certain existing municipal areas and industrial estates or industrial areas. For high-rise buildings, the fire-access and open-space requirements apply despite the ordinary setback rules. They generally require a motorable approach and open space at least 6.00 m wide on all sides, subject to the specific conditions in the fire provision. See Regulation 4.4.2(a)–(b), Regulation 15.1.2 and Setbacks and Projections.
Buildings on Stilts, Basements and Sloping Ground #
Stilts are a portion of a building with at least two fully open sides. A parking stilt that occupies the entire floor has a maximum floor height of 2.85 m under the definition. Parking stilt floors should have adequate ramp or mechanical access. Regulation 2(126)
For a building on ground-level stilts or with a basement, the starting level is the top of the stilts or basement under Note (2). This is the upper level of that portion, rather than the parking or basement floor below. See Mezzanines, Lofts, Attics and Basements for the separate basement dimensions. Where a ground floor is partly on stilts and partly covered, the height starts at the top of the stilt floor in the stilted portion and at adjoining ground or road level in the covered portion. The whole building may be treated as on stilts if its stilt area exceeds 75% of its plinth area. A stilt area of exactly 75% does not meet this condition. Regulation 6A.5(a)(i)–(ii) and Note (2) · 9 August 2023 Gazette, first notification §5
One stilt floor at ground level or another level is ordinarily excluded from building height. The VP2 limit described above for Regional Plan settlement areas includes the stilt. On a sloping site, the stilt height may be relaxed and an extra stilt level below the road may be permitted to avoid cutting or filling if no public access is drawn or available at the lower level. In Special Residential (SPR), Special Commercial (SPC) and C1 Special zones, two parking stilts are specifically excluded from the building-height calculation. These rules sit alongside separate provisions on floor area, parking and fire safety. Table VIII Notes (12), (25) and (26)
Where the Ground Slopes #
A sloping site has a gradient greater than 10%. For buildings on different levels, the height rules address slopes up to and including 25%. The starting level can depend on where the plot is accessed. Regulations 2(124) and 6A.5(d)–(g)
Site condition | Starting level for the height measurement |
|---|---|
Building on different levels on a slope up to 25% | The building has separate plinth levels. Where the lower part is on stilts to maintain the floor level, the top of those stilts is the plinth level. |
Only one access, from the lower part of the plot | The average of the plot’s highest and lowest elevations is the plinth reference. |
Only one access or road, from the higher part | The road level is treated as adjoining ground level. |
Two or more accesses or roads | The clause allows varying heights measured at each level from adjoining road or ground level. See the qualification below. |
Source Regulation 6A.5(d)–(g) and Note (1). On a sloping site the plinth should be no higher than 1.50 m.
Editor’s note — starting level. The general opening uses 0.90 m above adjoining road level; Note (1) separately specifies a 1.50 m maximum plinth for a sloping site. The latter is the site-specific provision, but the text does not explicitly reconcile every access-based reference level with the general opening. Clause (g) also excludes categories (e), (f) and (g), thereby referring to itself. No correcting instrument was located. These issues affect the starting level, not the existence of the express measurement rules above. Where the result depends on that interaction or clause (g), the reference level needs competent-authority confirmation. Regulation 6A.5, opening, clauses (d)–(g) and Note (1)
With only one lower access, plot levels of 100.00 m and 106.00 m give a reference elevation of (100.00 + 106.00) ÷ 2 = 103.00 m. A roof measurement point at elevation 113.50 m gives a height of 113.50 − 103.00 = 10.50 m in that case. The calculation averages the plot’s highest and lowest elevations to set the starting level for the building-height measurement. Development on slopes steeper than 25% is prohibited under the separate slope rule. Regulations 6A.5(e) and 4.10(e) · Site Constraints and Sloping Land
Rooftop Features and Fire-Safety Height #
Features that are purely decorative are excluded from the height measurement. Elevated water tanks, stair cabins, lift cabins and other features serving only decoration or building services are excluded if the added height is no more than 7.50 m above the topmost level. The provision gives examples including water supply, air-conditioning, dish antennas, cellular towers and solar heaters. A feature of exactly 7.50 m meets the numerical condition if it also meets the use condition. Regulation 6A.5(c)
For fire safety, the height provision refers to terrace level. The high-rise definition starts at 15.00 m, irrespective of occupancy. A building on stilts or with a basement is subject to Fire and Life Safety Regulations if it reaches 15.00 m from the ground, even if the height measured from the top of the stilt or basement is lower. Regulations 2(20A)(h), 6A.5(c) and Note (2) · 9 August 2023 Gazette, first notification §§2 and 5
For example, with ground at elevation 100.00 m, the top of a stilt floor at 102.70 m and the terrace at 115.00 m, the height above the stilt floor is 115.00 − 102.70 = 12.30 m. The terrace is 115.00 − 100.00 = 15.00 m above the ground, so the fire-safety threshold applies.
Fire-clearance requirements can also apply below 15.00 m. Educational and institutional buildings at exactly 9.00 m or higher meet their own height trigger. Other triggers include assembly occupancy, more than 300 m² of incidental assembly occupancy on any floor, and two or more basements or a single basement over 500 m². Floor area over 500 m² on any one or more floors is also a trigger in the hotel, educational, institutional, business, mercantile, industrial, storage, hazardous and mixed occupancies listed in the provision. Alterations, modifications or renovations exceeding 500 m² in a high-rise building also require fire clearance. High-rise fire access and open-space rules take precedence over the specified ordinary access and setback provisions. See Fire Safety and Life Safety. Regulations 15.1.1–15.2.3 · Setbacks and Projections
The industrial access table in Annexure XII pairs its small-industry entries with two storeys and places other industry under permissible height. The 2025 amendments leave those storey entries in place. The latest industrial footnote requires the road-widening area specified in the Regional Plan or Outline Development Plan to be left. On the same plot, height can also determine the required spacing between buildings when facing sides take light and ventilation, as well as the dimensions of certain courtyards. Table VIII Note (16), Annexure XII and Regulations 4.4.2, 4.8–4.9 · 4 September 2025 Gazette §2 · 24 December 2025 Gazette §2
Special Places and Building Types #
Coastal Regulation Zone land is governed by the applicable CRZ regulations. In a notified conservation area, the existing skyline and roofing pattern are generally to be followed. Table IX gives Panaji’s conservation-area height entries as 12.00 m for commercial buildings and 7.60 m for settlement and institutional buildings, with storey limits shown beside them. A stepped additional floor may be allowed in special cases up to a total of 15.00 m in the commercial area or 9.00 m in the settlement area. In Margao, the central commercial entry is 9.00 m to the eaves and 10.50 m overall, and the local commercial entry is 8.00 m to the eaves and 9.50 m overall. The settlement entry is 7.60 m to the eaves. Table IX also sets storey limits and has a separate institutional entry. Development in Conservation Zone F is referred to the Conservation Committee, whose decision binds the planning authorities. Table VIII Note (9), Regulations 6B.1.1 and 6B.1.8, and Table IX
A shopping mall with a multiplex and assembly occupancy is limited to the lower of 30.00 m and the zone’s limit. In C1 Special, CS and SPC only, a landmark or iconic tower may qualify for a relaxation to 50.00 m with Town and Country Planning Board approval and applicable setbacks. The tower must be non-assembly use and cover no more than 33% of the mall and multiplex plinth area. An attached tower needs separate ground-level entry and exit, and the overall building cannot exceed 50.00 m. A detached tower in the same compound can be considered independently up to 50.00 m. Additional height depends on suitable Fire Services equipment, subject to the potential exemption for equipment donation and in-house firefighting facilities described in the note. Regulation 5A(4)
A farmhouse in A1 or A2 is limited to 7.60 m from ground to eaves, including any stilts. A height relaxation can be considered for specific needs such as smoke houses. The farmhouse must have a sloping roof clad with Mangalore tiles. Farm, poultry or animal sheds and similar structures have a separate roofing-material allowance. Table VIII Note (4) and Annexure XI, item 4 and notes
Under Annexure XIII item (2)(ix), eligible four- and five-star hotels using that separate route may be considered for one additional floor up to 24 m. Government may consider up to 28 m in C1 on the merits with parking and fire safety. This route is separate from 6.1.2. An eligible educational institution using the Annexure XIV FAR benefit can receive a height relaxation with case-by-case Government approval. The annexure allows only one additional floor and requires fire clearance at any height when the benefit is used. Its eligibility and approval conditions continue to apply. Table VIII Note (22) and Annexure XIV, items (4), (5), (8) and (12)
Certain Government and public schemes may obtain a written, public-interest relaxation of maximum height and minimum setbacks. Older non-high-rise buildings may qualify for a hardship relaxation for additions or alterations where development was already completed or partly completed before the regulations came into force. Written reasons are required and FAR and setback-line projections cannot be waived under that provision. Regulations 22.2 and 22.4(b)
A separate provision allows the competent authority to regularise minor deviations due to site conditions if the deviations stay within 5% of the permissible FAR, coverage and building height. It includes a fee exception for a qualifying height increase up to 5% or an overall shift that reduces the required setback by no more than 5%, where no floor area is added and the work complies with the tall-room rule. It addresses regularisation of actual deviations. Regulation 22.5 and note, and Regulation 13.1(b)
Aerodrome safeguarding can impose a separate ceiling on structures. Civil aviation height restrictions use their own applicable rules and clearances. Annexure VII of the Goa regulations reproduces National Building Code 2005 material for reference and information only. Its general height and roof-feature provisions are not used here as operative substitutes for the Goa measurement rules. Civil aviation height restriction amendment rules · Annexure VII, introduction and paragraphs 11–12
How Much of a Roof May Be Flat? #
The roof-form rule applies to all buildings in a residential zone. These buildings should have sloping roofs. A flat roof may be permitted for up to 50% of the covered area of each building. The allowance applies building by building and the 50% is a ceiling on what may be permitted. Covered area is the area covered immediately above plinth level, subject to the specific exclusions in its definition. It is a building area in square metres, distinct from coverage expressed as a percentage of effective plot area. Regulations 4.1(c), 2(43) and 2(44) · 4 August 2011 Gazette, §12
For a building with a covered area of 160 m², the maximum flat-roof area that may be permitted under this clause is 0.50 × 160 = 80 m². A flat-roof area of exactly 80 m² is at the ceiling for that building. A second building on the same plot with a covered area of 100 m² has its own limit of 0.50 × 100 = 50 m². Each flat-roof area is assessed against its own building’s covered area. Regulation 4.1(c)
Editor’s note — mixed roofs. The roof-form clause sets the area limit, while the building-height clause gives separate measurement points for flat and sloping roofs. The provisions do not say how to choose a single controlling height where both roof types occur on the same building. The roof-form clause does not specify a minimum pitch or a separate method for measuring flat-roof area where roof edges extend beyond the covered area. Regulations 4.1(c) and 6A.5(a)–(b)
GBC Wiki is an explanatory reference. Verify the current official provisions and applicable authority requirements before making a regulatory decision.