Subdivision and Plot Layout

Editorial review

A-012 · R01 · Awaiting human acceptance

Send feedback on this article
On this page
  1. Which land is being divided?
  2. Access to the land and individual plots
  3. Road construction and drainage
  4. Sloping land and open space
  5. Amenities in larger layouts

Subdivision divides a plot into smaller parcels. Approval depends on how each parcel will be reached and drained, which land is usable for construction, and how roads, open space and common facilities will serve the layout.

Which land is being divided? #

Regulation 2(133) excludes easements to dominant lands, involuntary fragmentation by Government schemes or family inheritance and divisions under the Mundkars Act. Amalgamation creates a continuous parcel in one ownership; separate chalta numbers within one commonly owned plot need not always be amalgamated. [2(2), (100), (133).]

Regulation 12 governs new subdivisions. Its opening treats A1/A2 separately and refers to 12.7; agricultural zoning restrictions remain applicable. Existing original plots with independent survey/chalta numbers do not have to satisfy the subdivision minimum plot size and frontage merely for development within the original plot. The layout must provide for refuse, sewerage, water, power, telephone, cable and other essential services.

Access to the land and individual plots #

A right of way includes the carriageway, shoulder, footpath and drains. The carriageway is the surfaced traffic portion. Each plot and open space needs independent motorable access from a public road, drainage against flooding and corner boundary stones. A plot’s front is its side abutting the access street, subject to the plot-type rules in 2(100). Road Access Requirements explains building approach; the tables below concern subdivisions. Tables XII–XIV distinguish plot dimensions, the approach to the whole site and the internal roads. [2(30), (65), (113), (128), 12.5–12.6.]

Minimum plot sizes (Table XII)

Zone

Area (m²)

Minimum side (m)

S1–S4

225

15

C1–C4

500

20

I1

600

20

I2

1,000

25

I3

5,000

50

P

1,000

20

T

1,000

25

R

500

15

A1/A2

4,000

20

Existing independently surveyed or already approved plots at adoption are excepted. When further subdividing an approved plot, a side may be relaxed to 10 m if each resulting plot is at least 200 m². [12.6(b).]

Road to the subdivision (Table XIII)

Effective area (m²)

Other zones

I1–I3 and T

Up to 7,500

6 m

10 m

7,501–20,000

8 m

10 m

20,001 and above

10 m

15 m

For an existing plot up to 5,000 m² abutting a public road only 3 m wide, the approach requirement may be relaxed if its length from the main road does not exceed 100 m.

Roads within the layout (Table XIV)

Area served (m²)

Looped

Cul-de-sac

Up to 2,500

6 m

6 m

2,501–5,000

6 m

8 m

5,001–20,000

8 m

10 m

Above 20,000

10 m

12 m

In settlement a 3 m road may serve one plot no larger than 500 m² without a turning head. For industrial/transport use the minima are 10 m looped or 15 m dead-end; for commercial use they are 8 m or 10 m respectively. Editor’s note. The introductory sentence of 12.6 cites XIII–XV. The three printed schedules beneath it are XII–XIV. Their subject headings identify the applicable values.

Road construction and drainage #

Road cross-sections (Table X)

Right of way

Carriageway

Shoulder each side

Drain width

6 m

3.5 m

1.10 m

0.30 m one side

8 m

4.5 m

1.35 m

0.40 m each

10 m

7 m

1.10 m

0.40 m each

15 m, median

9 m, median

2.50 m

0.50 m each

20 m, median

12 m, median

3.50 m

0.50 m each

Longitudinal road gradient ordinarily cannot exceed 1:8. If a gentler road is infeasible, relaxation to 1:6 may be considered over no more than 100 m with a higher-specification, non-slip road surface. Internal roads require water-bound macadam with asphalt topping to PWD specifications. Corner radii are 3 m through 10 m right of way and 5 m above; at unequal roads the wider standard applies. A cul-de-sac head is at least 12 × 12 m, touching the plot boundary to serve adjoining property, subject to the single-plot exception. Subdivision roads are deemed public except in the specified cooperative housing/maintenance society or gated community. [12.1 and Sketches 1, 3.]

Drains require sufficient fall and PWD lining and finish. Provide at least the Table X widths, on one side through 6 m right of way, both sides above. Site-specific cross-drains and culverts use pipe at least 300 mm in PCC or an RCC slab drain on laterite masonry with PCC lining. The plan shows flow paths and final discharge to public drains, nallahs or natural channels, and construction sections. Open spaces need approved lined drainage. [12.2.]

Sloping land and open space #

For gradients of 1:10 or more, show block levels at 5 m centres or a chartered surveyor’s 1 m contours tied to an identified benchmark. Chartered-surveyor levels or contours are obligatory above 10,000 m². Land steeper than 25% cannot form usable development plots, subject to the exception for subdivisions approved before commencement. [12.3.]

At 4,000 m² and above, S1–S4 reserve 15% usable open space under Table XI. Regulation 18.3 separately describes landscaping for plots exceeding 4,000 m². The wording in 18.3 does not change Table XI’s inclusive trigger. C1–C4 and P reserve 10% recreation and 5% open-to-sky general parking. Industrial I1–I3 at 10,000 m² and above reserve 7.5% each for recreation and open parking. T at 20,000 m² and above reserves 10% recreation and 5% open parking. In GIDC-developed industrial estates/areas the special reservation is 7.5% total: 2.5% recreational landscaping and 5% general utility/open parking; released excess is deemed industrial. GIDC may realign, revise or reduce its existing estate spaces to the prescribed standards. [12.4(a), Table XI.]

Reserved open space cannot be further subdivided. Multiple parcels must each be at least 500 m² with sides at least 15 m; an irregular or triangular parcel must contain a 15 m diameter circle (Sketch 7). Each needs access as an independent plot. Recreation and community use serve the occupants. Utility installations may cover 5% of each parcel or pool those allowances into a larger reserved parcel; maintain 3 m setbacks and 6 m maximum height, with a height exception for water towers. Spaces are deemed R. A gift before final approval transfers maintenance to the local authority and purchasers retain free use. In group housing the owners or society hold proportionate undivided shares and the permitted use continues. Boundary walls must preserve adjoining access. [12.4(b)–(e).]

In commercial zones, parking by-lanes along public roads at least 7.50 m wide may supply up to half the required open space. For partial development, reserve 15% of the portion developed only where that portion and the balance are each at least 4,000 m². General pool parking must stay open to sky and unbuilt. [12.4(f)–(h).]

Amenities in larger layouts #

Settlement layouts with effective area over 5 ha and below 50 ha reserve 5% of total plot area for amenities and utilities. [12.7(a).]

The reservation is distinct from usable open space under Table XI.

For a proposed or revised subdivision, the listed amenities include schools, community and commercial centres, sports complexes, parking and charging, health clubs, hospitals, nursing homes, dispensaries, post and police stations, electrical substations, bank ATMs, libraries, open markets, garbage bins and material recovery facilities, assisted living and hospice together, senior citizen housing and orphanages, housing for project-affected persons, water and electricity installations, and other utilities and services.

The owner retains ownership until a transfer for development for the earmarked purpose.

The earmarked use remains unless changed to an amenity within clause (a)(i).

The authority may also impose conditions for drainage, waste, water supply and other amenities or common facilities.

In I1, I2, I3 and T, layouts with effective plot area between 2 and 5 ha reserve 5% of total area for parking, fuel/POL dispensing, garbage disposal and scrap yards. [12.7(b).]

Above 5 ha the reserve is 7.5% for those activities plus retail, post office, bank and other ancillary commercial activities. An additional 10% may be reserved for industrial housing. [12.7(c).]

Industrial estates and industrial areas reserve an additional 5% of total plot area for utility installations including post offices, telephone exchanges, substations and electrical offices, drainage, public toilets and pollution-control laboratories only where set up by the Pollution Control Board or Government. [12.7(d).]

See the official GLDBCR, Regulation 12, Tables X–XIV and Chapter 28, Sketches 1, 3 and 7. Check the current official regulations and plan before making a regulatory decision.