  1. Acquisition for an institution or shared service
  2. Accommodation reservation and land pooling
  3. Which regulations govern completion of an older approval?

Acquisition, accommodation reservation and land pooling each make land available for a public purpose in a different way. One involves the competent authority acquiring land, another exchanges a completed amenity for development potential, and another redistributes plots after a layout is planned.

Acquisition for an institution or shared service #

A zone is the land-use classification in the relevant development plan. Regulation 4.12(a) allows the competent authority, at an institution’s request, to acquire land zoned P (public, semi-public and institutional) or R (parks, playgrounds and recreation) for development allowed in that zone. The extent is tied to the minimum plot size specified for the zone. A different limb lets the authority define and acquire land needed for a common facility or service, such as a crematorium or cemetery, at an institution’s or local body’s request, for a use permitted in the specific zone. [2(149), 4.12(a)–(b).]

Accommodation reservation and land pooling #

Under 25(B), owners of a site reserved in a plan for an amenity can develop it using its full FAR on agreeing to deliver the amenity to the local body free of encumbrances and accept that FAR as compensation. This mechanism concerns land already reserved for the amenity in the plan.

Pooling requires participating owners, a planned and approved layout identifying both original and final plots, redistribution and compensation for land used for public purposes and transferred to the local body. The provision relates the technique to shortages of land and public services and the relocation of activities from congested centres. It names warehouses, godowns, petrol pumps, service workshops, repair garages, waste treatment plants, crematoria, cemeteries, burial grounds and scrap yards as possible activities. It gives no universal compensation rate or final-plot percentage.

Transfer of development rights has a separate basis in 25(A), including designated receiving areas. See Floor Area Ratio for the circumstances governing transfer. A pooling proposal by itself does not confer a transferable credit.

Which regulations govern completion of an older approval? #

Where the competent authority approved a subdivision or building and development was completed or partly completed pursuant to that approval, final approval, completion order or occupancy certificate is governed by the regulations on which the approval was granted for up to six years. A further maximum six years requires an extension on written request, giving appropriate grounds within the licence validity period. Approvals, Construction and Occupancy explains the distinct approval and occupancy stages. The original approval, work undertaken and timing all matter. [21.2.]

Regulation 22 supplies separate, scoped relaxations, including those for EWS housing, qualifying older buildings and specified industrial and Government projects. These provisions do not generally preserve every earlier standard indefinitely. Earlier additional-FAR or height grants are separately subject to examination under 6.1.2(e). [24 November 2026 Gazette.]

See the official GLDBCR, Regulations 4.12, 21.2, 22 and 25(B). Check the current official regulations and applicable notifications before making a regulatory decision.