  1. Mining, quarrying and brick kilns
  2. Fuel and vehicle service stations
  3. Assembly, burial and energy structures
  4. Hoardings near roads and on roofs
  5. Trees and landscaped open area
  6. Natural hazards and structural safety

Quarries, fuel stations, cinemas, burial grounds, signs and similar development have rules that can affect where they fit on a plot or whether they can be proposed at all. Landscaping and hazard safeguards also apply to ordinary development.

Mining, quarrying and brick kilns #

The separation is at least 50 m from the boundary, any public road, railway line, canal or building when no blasting is involved. With blasting it is at least 200 m. In that case the building restriction is for habitable buildings and the text excepts non-habitable structures related to quarry operations. No operation is permitted within 500 m of the High Tide Line in coastal areas. Permission is for a stipulated period of at most three development-permission terms. [GLDBCR Regulation 7(a)–(c), (g).]

Operations must protect nearby foundations and the stability of hills, slopes and embankments. Regulation 7(d) says operations are not permitted substantially below average ground level. It also requires a Geotech Consultant’s feasibility report for stone, earth or murrum extraction. At expiry the land is restored to its prior condition after soil conservation in accordance with the consultant’s report. The competent licensing authority can stop work detrimental to the environment, public health or local safety. [7(d)–(f), (j).]

The Regulation 7 site plan is submitted in quadruplicate with 5 m contours by a Chartered Surveyor and the consultant’s report. Goa State Pollution Control Board approval or NOC precedes the local body licence or NOC application. For engineering, mining and quarrying applications, 3.2C2 also requires a site plan at 1:1,000 or larger with boundaries, north, existing structures on, over, under or projecting beyond the site, natural features, street access and its width, and the operations proposed. It also calls for a location plan with written distances and landmarks, plans and sections for cuts or fills over 1.50 m, a surveyor’s contour plan at 1 m intervals on sloping land, and Forest Department permission where applicable for tree felling. Both contour provisions appear in the regulation. [7(h)–(i), 3.2C2(a)–(e).]

Fuel and vehicle service stations #

A filling station dispenses essential fuels or motor oil for vehicles, including CNG and LPG. A service station services vehicles for normal operation. A combined station performs both functions. The servicing definitions cover oil, tyres, batteries, accessories, washing and lubrication, and exclude body or engine repairs, painting, other major repairs and overhauls. [2(58), (59), (121).]

All four station types use the same intersection distances, measured from the tangent point: at least 45 m for minor roads and 90 m for major roads. For this purpose a major road has a right of way of at least 20 m. IRC norms govern conflicts with Regulation 8.

Facility

Minimum plot and frontage

Minimum parking

Fuel filling

600 m² effective, 30 m frontage. In C1–C4, 500 m² and 25 m may be allowed

One space per 600 m² or part, minimum two

Filling and service

1,000 m², 30 m frontage

Four spaces for the first 1,000 m² or part, plus one per additional 200 m² or part

Service

500 m², 25 m frontage

Same as filling and service

Wayside facility with filling and service

8,000 m² effective, 50 m frontage

Same as filling and service, plus the required parking for other activities

Source. GLDBCR Regulation 8(A)–(E). A filling-station plot is level except in hilly terrain. Its pump island needs 6 m from the effective front boundary, 10 m on each side and 6 m from above-ground built-up area on the plot. The competent authority decides location and setting and directs drive kerbs and kiosk location. All four types are subject to the petroleum fire-safety rules as amended or substituted. Regulation 8(E) names the Petroleum Rules, 1976, subject to that substitution.

Assembly, burial and energy structures #

Regulation 9.1 refers cinemas, theatres, motion-picture houses, exhibition halls and other NBC Group D public assembly buildings to NBC Part 4 fire and life safety, IS 4878 for cinema construction and the Goa Cinematography Rules. Regulation 9.1 cites NBC 2005 as amended, while Regulation 15 expressly applies NBC 2016 Part 4 to the buildings it covers. The project’s assembly and fire-clearance duties also arise under 15.2.

The safety buffer from the cremation platform to the nearest settlement area is 30 m. For cemeteries and graveyards it is 15 m from the graveyard. Proposed facilities must accommodate the buffer within their own plots. For an existing crematorium the buffer may be relaxed to 15 m, case by case, on a specific request put before the Board by the Chief Town Planner with comments. [9.2.]

Structures proposed for installing non-conventional energy are exempted from coverage, FAR, height and use under 9.3. The note under 9 treats buildings or structures that the GLDBCR does not specifically define or cover as special buildings dealt with under the NBC.

Hoardings near roads and on roofs #

An advertising sign is an outdoor surface or structure for advertising or public information as described in 2(8). A hoarding includes a display structure erected on the ground, on a roof or on or above a parapet. Permission comes from the corporation, municipal council or village panchayat, with the plot or building owner’s NOC and any other relevant permissions. The design accounts for wind, dead, seismic and other loads. [2(8), (78), 17.1–17.2, 17.9.]

Road right of way

Maximum vertical × horizontal size

Setback from right-of-way line

Over 50 m

5 m × 15 m

10 m

20–50 m

3 m × 12 m

5 m

10–20 m

2.5 m × 10 m

3 m

Source. GLDBCR Regulation 17.3. The heading above the printed table is Table XXIII although the clause calls it Table XXIV. Both bands include 20 m as written. Editor’s note. The text supplies no tie-breaker at that width. Regulation 17.5 rules out widths below 10 m.

Roads below 10 m are excluded. The top of a roadside hoarding may not exceed 10 m above ground, and its bottom is at least 3 m above the highest point below it. No hoarding is permitted within 100 m of an intersection, measured from the intersection of the adjacent right-of-way edges as shown in Chapter 28, Sketch 5, or within 100 m either side of a bend of less than 135°. Words or displays resembling traffic commands or signals require specific permission. [17.4–17.7.]

On roofs, the stated size is 1 × 2.5 m subject to a maximum of 2.5 × 10 m. Roof hoardings may not project beyond the existing building line. A cluster may have up to five hoardings at least 5 m apart, with at least 200 m between clusters. The note calls for municipal or corporation guidelines in consultation with the Conservation Committee. Access and Circulation Within a Plot explains the separate sightline rule. [17.8–17.10 and Note.]

Trees and landscaped open area #

Development preserves existing trees as far as practicable and replaces each felled tree with two. Each plot must have at least one tree for every 100 m² or part thereof, planting any shortfall. Individual plots taken up for development reserve at least 15% of the plot area for landscaping after allowing for coverage, parking, circulation, access and services. [18.1–18.2, 18.5.]

For subdivision development over 4,000 m², Regulation 18.3 connects the 15% open-space reservation with landscaping and roadside avenue planting by the developer. The roads and space may be transferred to the local authority for maintenance. Purchasers retain free access and use of that space. Below 4,000 m², 18.4 describes no subdivision open-space reservation but requires avenue planting and refers to handover to the local authority. The two clauses use strict inequalities. The applicable subdivision provisions and their thresholds govern the layout. The 15% landscaping rule for individual plots in Regulation 18.5 is separate from the subdivision reservation. [18.3–18.4, 12.4.]

Natural hazards and structural safety #

A natural hazard is the probability of a potentially damaging natural event within a given area and period. Hazard-prone areas include those exposed to moderate or high earthquakes, cyclones, significant flooding, landslides and similar movements. Infill, glazing, cladding, parapets and chimneys can be non-structural components even though they still present safety concerns. [2(87)–(89).] The note to 2(88) points to IS 1893 seismic zones III–V for moderate to very high earthquake damage risk, to coastal wind of 39 m/s or more under IS 875 Part 3, and to the Flood Atlas and relevant local surveys for flooding. Landslide areas are identified in the State Disaster Management Plan.

Regulation 19 identifies Goa with Seismic Zones II and III and calls for earthquake-resistant Indian Standards and guidelines. It calls for avoiding development as far as possible of flood-prone, landslide-prone and other non-developable areas identified in the State Disaster Management Plan and other plans of the Goa State Disaster Management Authority. Site Constraints and Sloping Land explains the separate site controls.

Structural design and retrofitting under 3.6.2(e) are reserved to the Structural Engineer on Record or Structural Design Agency on Record, with proof-checking by the competent authority wherever applicable. The clause lists NBC structural design and Indian Standards for materials, loads, foundations, wind and cyclones, earthquake resistance and slope or retaining-wall hazards. Its closing note calls for the latest revision unless it specifies particular criteria.

Additional FAR or height under Regulation 6.1.2(c)(ii) requires verification of structural safety before application. In an existing building the applicant must also ensure that the structure can safely support the additional development. See the 24 November 2026 Gazette and the article on Floor Area Ratio for the other conditions of the grant.