Special Housing Schemes and Existing Buildings
A-025 · R01 · Awaiting human acceptance
On this page
Different concessions apply to economically weaker section housing, older buildings, tribal housing under Atal Asra Yojana and cooperative redevelopment. The age of an existing building or the name of a scheme alone does not establish eligibility.
Economically weaker section housing and older development #
For EWS subdivision or building work by local authorities, State or Central Government departments, the Housing Board, PDAs or private developers, the competent authority may record written reasons and reduce minimum plot size to 60 m² and relax maximum coverage up to 60%. [22.1.]
For additions or alterations to non-high-rise buildings only, hardship may arise because development was complete or partly complete before the regulations came into force. On the merits, with written reasons, the competent authority may relax or waive requirements, except FAR and projections within setback lines. Where an existing building already covered at least 60% before commencement, proposed coverage or combined existing and proposed coverage may be relaxed up to 10% over and above the permitted coverage. Editor’s note. Regulation 22.3 does not state whether the increment is ten percentage points or ten percent of the permitted figure. [22.2–22.3.]
Regulation 2(112) defines repairs/renovations by their internal effect: they may not materially affect the exterior or violate existing coverage, right of way, setbacks, FAR or height. Structural stability must remain intact; the Directors of Panchayats and Municipal Administration prescribe the procedure.
Atal Asra Yojana #
Annexure XV applies to tribal houses. Municipal areas and PDA planning areas are excluded, as are coastal villages except Cola, Agonda and Velim. Construction, reconstruction and repairs should, as far as possible, conform to Settlement land use in the Regional Plan 2021. Eco-I land excludes new construction. Repair, renovation or reconstruction of an existing house on forest land or in the 1 km buffer may be permitted with a Forest Department NOC. [Annexure XV(1)–(2), (14).]
For repairs and renovations, deficient existing access and setbacks may be relaxed. For new work or reconstruction where plot size or ground conditions prevent normal setbacks, at least 1.5 m road access and 1 m side setback remain. Relaxation requires NOCs from the immediate affected plot owner. All scheme work is limited to a 100 m² plinth, ground plus one floor and 150 m² total built-up area. A new plot must measure at least 60 m². Reconstruction coverage may not exceed 60% of effective plot area. [Items 3–5, 9, 11.]
Item 6 dispenses with the existing licence copy and sanad on submission for repair, renovation and reconstruction. Item 7 separately permits the Technical Clearance for new work or reconstruction to be conditioned on obtaining the sanad unless exempt under the Land Revenue Code. An existing unrecorded house requires branch Town Planning Officer inspection and a report with sketch confirming existence to the Senior Town Planner. [Items 6–8.]
The applicant should own the land or have the owner’s irrevocable NOC. Alternatives include proof of mundkar status, a competent authority’s licence or, failing these, other proof of the right to build satisfactory to the Senior Town Planner. Infrastructure tax and other construction fees do not apply under this scheme. [Items 10, 12–13.]
Cooperative redevelopment and Government schemes #
The explanation to 6.1.2 applies the additional FAR and height provisions to redevelopment by a cooperative society under section 104A of the Goa Co-operative Societies Act, 2001. Government may relax conditions further case by case. Under 6.1.2(c)(ii) an existing structure must safely support the proposal. A society resolution alone cannot establish a relaxation. See Floor Area Ratio for the common conditions.
Separately, 22.4(b) concerns Government and specified Government-scheme projects, including those executed by or on behalf of Government on PPP or other modes. Under 22.4(c) Government may grant additional FAR to projects within the preceding industrial or Government provisions for the specified fee. This clause gives no general fee-based entitlement to private housing. [24 November 2026 Gazette.]
See the official GLDBCR, Regulations 2(112), 22.1–22.4 and Annexure XV. Check the current official regulations and applicable notifications before making a regulatory decision.