An industrial zone on a plan and a plot belonging to the Goa Industrial Development Corporation (GIDC) raise different questions. The zone controls the use and building envelope. GIDC ownership or location in a notified estate can change the approving authority and which relaxations can be considered.

Industry, estate and approving authority #

A clean industry emits no smoke, noise, offensive odours or harmful industrial waste. An obnoxious and hazardous industry creates nuisance around it through smell, smoke, gas, dust, air pollution or other unhygienic conditions. GIDC is the statutory corporation under section 3 of the Goa Industrial Development Act, 1965. Its committee is constituted under section 37B(1). “Industrial estates and industrial areas” includes estates and areas developed by or vested with GIDC, their premises available for allotment and undeveloped land owned or held by GIDC. [Regulation 2(35), (68A), (68B), (73A), (92).]

Regulation 24 refers to the 22 February 2001 notification under which local-authority building controls ceased to apply in industrial estates. Permission for development in notified GIDC estates comes from the respective GIDC authorities, which apply the GLDBCR to existing and proposed estates.

Zone, use, coverage and access #

I1 excludes extensive, heavy and noxious industries; I2 excludes noxious and hazardous industries; I3 excludes non-industrial uses subject to the express auxiliary-use exceptions. The August 2026 substitution distinguishes 15% of permissible FAR for listed industrial auxiliary uses from 15% of built-up area for the estate/industrial-area list. Staff accommodation requires a plot over 5,000 m² and is limited to 7.5% of built-up area. See Planning Areas, Zones and Land Use for both lists. [6A.2.1(c) and notes.]

The 29 November 2024 Gazette substituted 70% for the 60% industrial coverage entry in Table VIII. In the printed table I1 and I2 retain 50%; the substituted figure applies to I3. Industrial maximum height is relaxable according to processing requirements. The amended Note 3 provides for relaxation of FAR, setbacks, parking and coverage for plots belonging to GIDC with Government approval. It gives no automatic replacement figures. See Building Regulations by Zone for the baseline table. Road Access Requirements explains the industrial road-width and storey conditions under Annexure XII as amended in 2025. The removal of the proposed 10 m widening condition for small industry did not remove the existing-road thresholds or the prescribed plan widening.

Operational requirements and additional FAR #

Under 22.4(a), where processing, operations or plant and machinery installation creates specific needs, the competent authority may relax maximum height and minimum setback with written reasons. The Government/public-project route in 22.4(b) has different beneficiaries and a larger-public-interest test.

The 24 November 2026 Gazette added 22.4(c). Government may grant additional FAR to the projects covered by the preceding clauses, against the fee specified under 6.1.2. Separately, Annexure XIII-A Note 1 excludes GIDC industrial estates and industrial areas from the industrial category of its general schedule. Editor’s note. The two provisions have different scopes. No authoritative reconciliation or current fee order was verified; a project in an excluded estate cannot assume it qualifies for a road-band increase.

See the official GLDBCR, Regulations 22.4 and 24, and the 29 November 2024 Gazette and 24 November 2026 Gazette. Check the current official regulations and applicable notifications before making a regulatory decision.