In a PDA area the first planning decision is Development Permission. In an area dealt with by the Town and Country Planning Department it is Technical Clearance. A construction licence from the local body follows the applicable planning decision. Conversion of land use under the Land Revenue Code is another decision with its own authority.
Planning approval and the local licence #
The “Authority” is the local body with jurisdiction over the matter. The applicable approved plan and the proposed work determine the route. Owners, including Government departments and semi-government or local authorities, generally follow the two-stage routes in 3.6.1. [Regulation 2(4), (36), (97), (98); 3.1.]
In a PDA area the owner submits Appendix A1-PDA to the PDA for Development Permission and, if a conversion recommendation has not already been obtained, A4. The application includes at least five sets of appropriate drawings and one document set. Applications, Drawings and Forms explains the supporting material. The local council, panchayat or corporation then receives the applicable A2 or A3 application, the PDA’s C1 order, three PDA-stamped and signed drawing sets and the documents under 3.2D. [3.6.1, Category I.]
In a TCP area the first application is A1-TCP for Technical Clearance and A4 for conversion recommendation, with the same initial drawing and document counts. The local application is A2 or A3 as applicable. The local body receives the C2 Technical Clearance, three sets stamped and signed by the Town Planning Officer and one set under 3.2D. Municipal and panchayat licence forms are C3 and C4. [3.6.1, Category II; 3.7.]
The ordinary permission requirement in 3.1 has a specific solar-farm exception, including construction, operation and office set-up subject to 2% of total farm area and a maximum of 200 m² per MW under the 2017 State Solar Policy. An Agriculture Department NOC and case-specific Government approval are required.
Conversion sanad and external authorities #
Under 3.2D(e), the file includes an existing conversion sanad or A4 seeking a recommendation, with four copies each of the area plan and the location plan. Annexure II refers the conversion procedure and fee calculation to the Goa Land Revenue Code, 1968. The recommendation and the sanad serve different purposes.
Under 3.6.2, coastal and Environment Protection Zone cases require prior coastal authority approval. Heritage and Conservation explains referral to the Conservation Committee before the planning decision for conservation and preservation proposals. For buildings within 15.2.1 the owner must obtain the Fire and Emergency Services NOC before applying to the local body for the construction licence. Railways, airports, military installations and other specified authorities may also require NOCs within their jurisdiction. Annexure I applies the Ministry’s environmental and CRZ notifications as amended.
Structural design and retrofitting under 3.6.2(e) are undertaken by a Structural Engineer on Record or Structural Design Agency on Record. Applicable designs and reports require proof checking by the competent authority. The regulation identifies structural, wind, earthquake and landslide standards and requires latest revisions except for specific criteria stated against a code.
Additional FAR or height #
On a plot of at least 300 m² in the areas specified in 6.1.2, the Government may grant additional FAR or height on the Board’s recommendation, subject to Annexure XIII-A, the Act, regulations and planned development. It may reject the application with reasons. Before applying, the applicant ascertains height-related setbacks, structural safety including the existing structure’s capacity, adequate parking and Fire Services conformity. The Fire Services NOC precedes the construction licence application. Charges specified by Government order are payable before Technical Clearance. Editor’s note. A current fee order under 6.1.2(b) was not verified. The earlier scheme’s rate is insufficient evidence of the amount now payable.
Annexure XIII-A Note 9 calls for a comprehensive project, sustainability and infrastructure report including water and power sources and supply. Note 10 requires a notarised non-four/five-star-hotel undertaking when road width is at least 8 m and plot area at least 500 m². Ordinary permission requirements continue under Note 5. See Floor Area Ratio for the full schedule. [24 November 2026 Gazette.]
See the official GLDBCR, Regulations 3.1, 3.2D, 3.6–3.7 and Annexures I–II. Check the current official regulations before making a regulatory decision.