GBC Wiki Regulatory sources
Beta testing*
Browse articles

Water, Drainage, Power and Rainwater Harvesting

Editorial review

A-018 · R01 · Awaiting human acceptance

Send feedback on this article
On this page
  1. Water supply and storage
  2. Wells and wastewater
  3. Electricity, solar and waste services
  4. Telecommunications rooms and underground ducts
  5. Where rainwater storage and recharge apply
  6. Extra services when additional FAR or height is sought

A building needs a safe water supply and a way to take wastewater away or treat it on site. Its size, use, utility connections and any application for additional FAR or height determine its storage, treatment, solar and other service requirements.

Water supply and storage #

Premises intended for habitation, occupancy or use require wholesome water protected from unsafe supplies and backflow. For new construction, reconstruction or alteration, public supply is generally linked to the competent authority’s construction licence or occupancy certificate. PWD can entertain a connection under its formalities and an undertaking that the connection does not legitimise an unauthorised structure. [GLDBCR 14.1.2(a)–(c).]

Pipe systems must prevent backflow without reliance on reflux or non-return valves. Where wholesome water backs up or mixes with a poorer supply, it must discharge into a cistern with an air gap of twice the nominal bore and at least 15 cm. WC taps and appliances need an air gap. Within 30 m horizontally of the building sewer, the bottom of the water pipe must be at least 30 cm above the sewer’s top at its highest point. Wholesome-water pipes cannot pass through drains, manholes or fouling material unless unavoidable and protected by approved casing. Nonconforming existing piping must be relocated. PWD specifications govern fittings and the regulation refers to NBC 2005 Part IX, Section 1 unless specified otherwise. [14.1.2(d)–(i).]

Occupancy or use

Litres per day

Residential / special residential

135 / 180 per person

Day schools / boarding schools

45 / 135 per person

Medical institutions with up to 100 beds / above 100

340 / 450 per head in Table XIX

Medical quarters and hostels

135 per person

Assembly other than restaurants / restaurants

15 / 70 per seat

Government or semi-public

45 per person

Commercial restaurants / lodging hotels / other business

70 per seat / 180 per bed / 45 per person

Industrial / storage and warehousing / hazardous

45 / 30 / 30 per person

Source. GLDBCR 14.1.2(j), Table XIX. Overhead capacity covers domestic use and flushing. Tanks or cisterns are watertight, covered and built of the specified reinforced concrete, GI steel, stone masonry or brickwork in cement mortar with internal cement rendering. Underground tanks must be drainable and protected from ponding. The overflow apparatus invert is at least 5 cm above the tank bottom. The draw-off prevents animals and insects entering, avoids sewer connection and leaves an open warning overflow. Domestic pipes are disinfected before use and after major repairs. Tanks and sumps require mosquito-proof lids and meshed vents under the Goa Public Health Act. Fire-water storage for multi-storeyed buildings uses the applicable NBC fire provisions. [14.1.2(k)–(q).]

Wells and wastewater #

Domestic wells must be at least 15 m from an ash or refuse pit, soak pit, earth closet or privy, with the well uphill of a closet or privy and sited to avoid contamination. Minimum internal diameter is 1 m, in sound permanent construction. Unlined irrigation wells are permitted only in fields or gardens. Well heads require a parapet at least 1 m high and 20 cm thick, outward-sloped impervious paving at least 1 m around it, and an impervious internal surface for 3 m below adjacent ground. Bucket wells require a stand at least 15 cm above paving. The Public Health Act applies to vector protection. [14.1.3.]

Sanitary and drainage installations require prior competent-authority sanction. Existing buildings connect to public sewers where available. In new construction, reconstruction or alterations, the PWD connection follows sanction of the permit or occupancy certificate. Without a public sewer, sanitary discharge uses a septic tank and soak pit, and wastewater a soak pit or adequately sized recycling or treatment unit. They lie within the plot away from wells and surveyed water bodies. WC and other wastewater use separate routes with inspection chambers and enough fall for smooth flow. Public Health Act controls and the referenced NBC 2005 Part IX, Section 2 as amended apply. [14.1.4(a)–(f), (h).]

Recommended household septic-tank criteria are 20–30 gallons per person with a 500-gallon minimum, length usually twice breadth, depth 1.50–2.00 m, liquid depth 1.20 m and at least 30 cm air space. Provide submerged inlet and outlet, a concrete cover slab and a manhole. Size the tank and soak pit for users. Septic tanks are discouraged for large communities. Editor’s note. The source pairs its gallon recommendation with 2.5–5 cubic feet per person. The numbers are not exact equivalents and the text does not specify a gallon convention. Kitchens need utensil washing with a trapped, grated waste connection unless supplied separately in a pantry. A suitably located, plumbed, cleanable sink uses the listed sanitary materials, no wood covering and a bottom that falls to the outlet. [14.1.4(g), (i)–(j).]

Residential complexes of 50 units or more require a sewage treatment plant unless existing sewer lines serve the area. Annexure V separately requires wastewater recycling for complexes discharging 10,000 litres per day or more, with horticultural use of recycled water in item 3(b). See also the additional development conditions below. [14.1.5 and Annexure V item 3(b).]

Electricity, solar and waste services #

A public electricity connection generally follows construction licence or completion certificate. A building likely to have multiple connections needs a 2 × 2 m ground-floor space nearest the public road. A building with at least 1,000 m² floor area requires a 2 × 3 m ground-floor room with fire barriers for transformer and distribution board, nearest the road, subject to Electricity Department permission. Where an underground system exists, multi-storeyed building proposals with at least 1,000 m² carpet area require a Government agreement and a 21 m² ground-floor outhouse (7 × 3 m) facing the public road for the departmental substation and switchgear, or as permitted by the department. The department can extend supply from it. [14.2(a)–(c).]

Line voltage

Vertical clearance

Horizontal clearance

Up to 11 kV

3.70 m

1.20 m

Over 11 through 33 kV

3.70 m

2.00 m

Extra-high voltage above 33 kV

3.70 m plus 0.30 m for each additional 33 kV or part

2.00 m plus 0.30 m in the 33 kV increments stated in Table XX

Source. GLDBCR 14.2(d), Table XX. Clearances apply to temporary and permanent structures. The extra-high-voltage horizontal row does not repeat the vertical row’s word ‘additional’. Electricity Department requirements matter for a specific line.

Regulation 14.3.1(a) requires an auxiliary solar-assisted water heating in new buildings in the listed categories where the relevant hot-water or solar system is installed: hospitals or nursing homes with at least 10 beds, hotels/lodges/guest houses with at least 20 beds, hostels/dormitories/barracks, group housing of at least 50 units, railway and airport functional buildings including waiting, retiring and rest rooms, inspection bungalows and catering units, and community centres, banquet halls and similar assembly uses. New plans reserve rooftop space and the required water supply. Solar-assisted heating or solar capture is mandatory on change to a listed use in an existing building and in industrial buildings. The government may give tax rebates in addition to applicable subsidies. [14.3.1(a)–(b) and Note.]

Rooftop PV under 14.3.1(c) covers group housing over 40 units, and educational, institutional, commercial, industrial, mercantile and recreational categories in the table’s plot band of 500 m² or more. The table also identifies other buildings under 2(20A) with shadow-free roof area over 50 m². The generation column gives the lesser of 5% of connected load and 20 W per square foot of available roof area. See the Gazette provision below for a separate scheme condition measured on sanctioned load.

For group housing on plots over 4,000 m² with at least 40 units, biodegradable waste treatment by aerobic treatment, vermicomposting or biogas is mandatory. Chambers for sorting waste may be covered by a structure up to 2.5 m high and open on at least two sides, excluded from coverage, FAR and setbacks. The site plan shows non-biodegradable waste collection and treatment spots. [14.3.3.]

Telecommunications rooms and underground ducts #

Regulation 14.3.4 requires building and roof areas with power for common digital infrastructure in new multidwelling, commercial, public and transport buildings. Where needed there is a 1.2 × 1.83 m area per provider next to the entry and underground encased conduits at least 100 mm in diameter to the main equipment room. The latter has a recommended 14 m² minimum, aspect ratio between 1:1 and 2:1, above natural ground, with lighting, ventilation, panels, isolators, sockets and earthing as specified. Building blocks need telecom rooms unless a main equipment room is supplied, appropriately sized risers accessible at every floor and telecom enclosures at each floor or telecom room.

For buildings over 465 m² built-up, the served-area table gives telecom-room dimensions 3 × 2.4 m up to 465 m² and 3 × 3.4 m from 465 to 930 m², with additional rooms beyond 930 m². For buildings below 465 m² built-up, up to 93 m² served uses wall or self-contained cabinets. The 93–465 m² row lists a shallow 0.6 × 2.6 m or walk-in 1.3 × 1.3 m room. The printed cutoffs overlap in served area and the building-size headings leave exactly 465 m² unassigned. Eligible room area is exempt under 2(63)(k). An undertaking by a competent professional certifies common access for providers and completion of the common infrastructure before occupancy or completion. [14.3.4 A.]

Subdivision plans show accessible telecom ducts, service points, spare capacity and empty future ducts laid before planting. Cables preferably go below parking or service lanes or else at the right-of-way edge. Telecom boxes leave a 2 m footpath. A competent professional’s undertaking is required before final subdivision NOC. Subdivision and Plot Layout explains surface and stormwater drainage. [14.3.4 B, 12.2.] Part 8, Section 6 of NBC 2016 (Volume 2) and the referenced model bye-laws addendum provide further detailing.

Where rainwater storage and recharge apply #

A harvesting structure collects and filters water for reuse or ground recharge. Annexure V item 1(b) defines a tank as underground storage and item 3 expressly addresses above-ground and underground tanks. A tank is covered storage, a reservoir is watertight open storage, and a permeable trench or recharge well promotes infiltration after filtration. Regulation 2(71)–(75), (114) and Annexure V item 1 define these systems, including roof-water harvesting and rock-strata filtration. Annexure V item 5 limits reuse storage to roof catchments under the cited WRD policy. Deep recharge is allowed only in WRD-designated areas. [14.3.2.]

Rooftop storage for secondary uses is mandatory for private buildings where plot area exceeds 4,000 m² and there are at least 40 units, for public or institutional complexes where plot area exceeds 4,000 m² and floor area exceeds 2,000 m², and for all commercial or industrial development on plots over 4,000 m². Other construction is recommendatory. Annexure V item 5 exempts the described users that incorporate an STP or recycling, and calls for a separate parallel line for secondary reuse. This exception is absent from Regulation 14.3.2’s main text. GIDC determines rainwater harvesting in industrial areas or estates case by case. WRD policy governs applicable subsidy.

Annexure V exempts eligible harvesting structures from FAR, coverage, height and setbacks if circulation and parking remain clear. Plans show system and collection points. Water is filtered and treated before non-monsoon use. Tanks must be watertight, covered and constructed of the listed masonry, RCC, metals or PVC/FRP with the specified internal finish. Underground tanks are drainable with no ponding, protected draw-off and warning overflow. Use mosquito-proof lids and meshed vents and disinfect collection lines at monsoon commencement and after the season or major repairs. Design criteria include twice as long as wide, at least 1.5 m depth, 30 cm air gap, 200 litres recommended per person and 10 m³ minimum capacity. Open reservoirs require containment, outflow weir to natural drainage, fencing and storage/reuse consistent with item 4. The Public Health Act specifications apply. [Annexure V items 2–5.]

Extra services when additional FAR or height is sought #

Annexure XIII-A makes rainwater harvesting mandatory under Note 6. Note 7 requires rooftop PV, solar water heating or both at a minimum of 5% of sanctioned load including existing load, regardless of plot area. Note 8 requires an STP where sewer lines do not serve the site and total water consumption including additional occupants exceeds 9.7 kL/day. Government may relax Note 8 for earlier grants. Note 9 requires a comprehensive project report covering infrastructure including water and electricity sources and supply. Floor Area Ratio explains the grant and its other conditions. [24 November 2026 Gazette, Annexure XIII-A Notes 6–9.]

Editor’s note. Note 7 prints 14.1.3(c), the provision for well parapets. The baseline solar provision is 14.3.1(c). The scheme’s own solar condition is explicit. Note 6 contains no express STP exception, so the Annexure V exception should not be presumed to extend to the scheme.

Check the current official regulations and applicable standards before making a regulatory decision.